Kitchen Remodel Cost in Henderson, NV (2026)
What a kitchen remodel actually costs in Henderson — Green Valley to MacDonald Highlands — with line-item budgets, City of Henderson permit fees and HOA review notes from our recent projects.
Based on Build4U's actual 2025–2026 Henderson project costs. NSCB license #0095372.
Quick answer
$35K – $195K+Most Henderson kitchens land in the $70K – $135K band.
Tier 1 — Pull and replace
$35K – $66KSame footprint, new cabinets/counters/appliances. Typical 150–220 sq ft Green Valley, Whitney Ranch or Inspirada kitchen.
| Demo + dump + protection | $2.3K – $3.9K |
| Semi-custom cabinets installed | $11.5K – $22K |
| Quartz counters + standard backsplash | $4.7K – $9.5K |
| Appliance package (mid-grade) | $4.7K – $11K |
| Plumbing + electrical (no relocates) | $3.1K – $5.5K |
| Flooring patch + paint + trim | $2.3K – $4.7K |
| City of Henderson permits + design + PM | $3.9K – $7K |
| Lighting + hardware | $1.6K – $3.1K |
Tier 2 — Layout change
$70K – $135KWall removal, island reconfiguration, expanded footprint. Seven Hills, Anthem, Madeira Canyon, Sun City Anthem.
| Demo + structural framing + engineering | $8K – $14K |
| Custom cabinets installed | $22K – $43K |
| Quartzite or premium quartz + slab backsplash | $9.5K – $17K |
| Pro appliance package (Wolf/Sub-Zero/Bosch) | $14K – $27K |
| Plumbing re-route + electrical re-route + new circuits | $8K – $14K |
| New flooring + ceiling work + paint | $4.7K – $9.5K |
| Permits + design + project management | $8K – $14K |
| Lighting design + hardware + accessories | $3.1K – $7K |
Tier 3 — Chef-grade
$135K – $195K+MacDonald Highlands / Ascaya / Dragon Ridge level. Slab stone, custom millwork, Wolf/Sub-Zero/Miele, butler's pantry.
| Demo + structural + steel beams | $14K – $23K |
| Full-custom millwork cabinets + butler's pantry | $43K – $74K |
| Book-matched slab stone counters + waterfall + full-height backsplash | $22K – $37K |
| Wolf + Sub-Zero + Miele package | $35K – $58K |
| Plumbing, gas, electrical re-route + dedicated circuits | $11.5K – $19.5K |
| Wide-plank or stone flooring + ceiling detail | $8K – $14K |
| Permits, engineering, plan review | $6K – $11K |
| Lighting design + smart controls + hardware | $6K – $11.5K |
| Design + project management | $15.5K – $27K |
Henderson permit + HOA notes
- City of Henderson — separate plan-review queue. Kitchen permits typically $500–$1,400 with plumbing, electrical and mechanical sub-permits. Plan review 1–3 weeks.
- Anthem Country Club — interior-only kitchen skips ARC; exterior vent or window change adds ~3 weeks.
- MacDonald Highlands / Dragon Ridge / Ascaya — strict ARC for any exterior element; plan 4+ weeks.
- Seven Hills, Madeira Canyon, Sun City Anthem — moderate ARC for exterior changes, ~2–3 weeks.
- Load-bearing wall removal — engineering letter + sealed plans required by Henderson plan review; add 1–2 weeks and ~$1.6K–$3.9K engineering.
Related
- Kitchen remodel cost in Las Vegas — same bands, Clark County permit notes.
- Kitchen remodeling in Henderson
- Our kitchen remodeling process
Next step
We'll put together an itemized estimate so you know exactly where every dollar goes before construction starts.
FAQs
How much does a kitchen remodel cost in Henderson in 2026?
Pull-and-replace kitchens run $35K–$66K, full layout-change remodels $70K–$135K, and chef-grade kitchens with island reconfigurations and slab stone $135K–$195K+. Henderson tracks Las Vegas closely; cost driver is finish level, not zip code.
Does the City of Henderson handle permits differently?
Henderson has its own Building & Fire Safety department separate from unincorporated Clark County. Kitchen permits typically run $500–$1,400 with plumbing, electrical and mechanical sub-permits. Plan review averages 1–3 weeks — often faster than the County on simple submittals.
Do MacDonald Highlands, Anthem CC or Seven Hills require HOA review?
Interior kitchen remodels usually don't trigger ARC review. Anything that moves an exterior window, adds a roof vent (range hood through-the-roof), or relocates an exterior door requires architectural approval — plan 2–4 weeks before permit submittal.
What drives a Henderson kitchen budget up the fastest?
Moving the island (plumbing + electrical re-route), opening a load-bearing wall (engineering + steel), slab stone counters and full-height backsplashes, custom millwork cabinets, and pro appliance packages (Wolf/Sub-Zero/Miele) — any one can add $11.5K–$31K.
How long does a Henderson kitchen remodel take?
Pull-and-replace 8–12 weeks on-site. Layout-change remodels 12–18 weeks on-site, plus 6–10 weeks of cabinet lead time and selections. Add 2–4 weeks for HOA review on exterior changes.